Scenario of multiple Asset from one AUC/WBS

Former Member
0 Kudos

Hello,

I am having a requirement, where I need to create multiple Asset from one WBS. I checked in the system and able to create more then 1 Asset for WBS.Also if I maintain the distrubution rules for those Asset then settle it accordingly to different Assets.

I just wanted to confirm, will it we the right way of handling this scenario? My main concern is this involves intervention of user for maintaing the settlement rule during final settlement.

Is there any other way to handle this scenario?

Thanks

Sarang

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

closed

Former Member
0 Kudos

hi, i am faced with a similar situation where we need to create multiple assets from single AuC.. As we go along the execution phase, the client wants to continue capitalizing the assets which are completed. could you let me know the solution you have offered for this.. sorry for opening the thread again.. but having to do so as it's the same situation..

virendra_pal
Active Contributor
0 Kudos

in the IM profile check the source str assignment box

then define the sources of costs which you want to roll into AuC in the settlement profiles

I would rather use different WBS elements to split the cost to different AuC - instead of rolling the WBS to the superior one

Former Member
0 Kudos

Hello Virendra,

I am not using Investment Managemnt. What do you mean by IM profile?

I understand that I need to maintain the source of cost in Source structure. But even in that scenario the user has to go and maintain settlement rules and create multiple Asset against one WBS.

So how do I tackle it, if client requirement is such that they want to create only one AUC, but during final Asset creation they want to create multiple Assets from one AUC. They dont want to have WBS for each Asset.

Thanks

Sarang