Hi,

Yesterday, I have scheduled the job but today, the job went to short dump.And I am loading the data from PSA.So I set the overall status to red and deleted the request from the ODS and again started the data loading from PSA.Now, all the datapackages are processed successfully, but transfer of IDOC's is still yellow status.

Can I do below Step:

1) Turn the overall status to green.

Or

wait untill all the IDOC's are processed successfully.

(And the dataload which I triggered after this infopackage is successful in transferring IDOC's and Processing.)

When I saw the dump I found the following message

How to correct the error

"MESSAGE_TYPE_X" C

"SAPLRSATREE " or "LRSATREEF28 "

"RSATREE_START_ACTIVATION"

I

Information on where termination occurred

The termination occurred in the ABAP program "SAPLRSATREE " in

"RSATREE_START_ACTIVATION".

The main program was "SAPMSSY1 ".

The termination occurred in line 536 of the source code of the (Include)

program "LRSATREEF28 "

of the source code of program "LRSATREEF28 " (when calling the editor 5360).

Please suggest me what will happen if I turn overall status to green?And start the next dataload.....

Regards,

Siva