on 03-27-2009 9:24 AM
I am from Sales Backround, and wanted to have an overview on Routing. Can any one please explain me what is routing ? and how and where its doing handshake with other modules? As this is for a knowledge shake i would request you to give more on Functional side rather than Tech stuff like T-codes etc...
Hi,
Routing is nothing but your Process Plan.
A routing is a description of which operations (process steps) have to be carried out and in which order to produce a material (product). As well as information about the operations and the order in which they are carried out, a routing also contains details about the work centers at which they are carried out as well as about the required production resources and tools (includes jigs and fixtures). Standard values for the execution of individual operations are also saved in routings.
Routings (generic) consist of the following objects:
- Routing
- Rate routing
- Reference operation set
- Reference rate routing
Routings enable you to plan the production of materials (products)
In a routing you plan
- The operations (work steps) to be carried out during production
- The activities to be performed in the operations as a basis for determining dates, capacity
requirements, and costs.
- The use of materials during production.
- The use of work centers
- The quality checks to be carried out during production
To Create one you have to proceeds with following steps:
1) CA01 - Create routing
First screen = Material on which you have to create a routing
Plant
Second screen = Usage 1 if you create routing for production purpose.
Status 4 release general
Enter
2) Now go on to application tool bar and select operation
Here you have to enter work center, control key and description
For eg. w/c 1 plant pp01 description
w/c 2 plant pp01 description
plant pp99 goods reciepts
3) Now select the component allocation
Select the material here and click on to the new assignemnt for assign the operation seqence on to the material.
4) SAVE
Now routing is create with routing group number .
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your valuable inputs..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Keeping the tech stuff out, a routing as a concept is to provide information as to how the material is to be manufactured. It gives the requisite details as to which work centers are required, what are the activities to be perfomed, the approx time required, if the operations are to flow in sequential or parallel operations are possible.
So in a nutshell, it works as a map.
Hope it was helpful.
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As Integeration aspect Routing is basis for ' Product Costing','Capacity' and 'Sceduling the Order'.
In product costing system calculate standard activity cost using information(M.C and Labour hrs) from routing.
System calculates Capacity and Sceduling useing routing data and formulae defined in wctr,
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.