Hi all,
I have a scenario that.service order is created in CRm linked with ECC,
so iam getting reservation in ECC currosponding to that service order.
when i plan with Fixed order qty (lotsize)and individual riquirement in ECC. i am getting PR relevent for that material reservation.( ican able to see in Pegged requirment)
i have other PR's which covers for safety stock.i want split PR which is relevent for safety stock and which is relevent for material reservation.
Question 1: can that safety stock coverd PR be a single PR ( if i set the master data Fixed order qty)
note : as reservation comes with fixed qty 1 i marked fixed lot size as "1"
Question 2: individual material reservation number required to be present in PR so that i will be have refernce while issuing against PO.How i can do it.
Question 3. to which table pegged requirement data stored.
Question 4: can i do config to make reservation number to get display in (relevent )PR in standard
Regards
s.suresh
Hi,
Question 3. to which table pegged requirement data stored.
Question 4: can i do config to make reservation number to get display in (relevent )PR in standard
As per my knowledge the pegging - information in R/3 is dynamic and not stored in a table.
With the function module "MD_PEGGING" and "MD_PEGGING_NODIALOG"
you can similar results as in MD04
Regards,
Sankaran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.