Planned Order Production Dates is not equal to Basic Dates

171 Views

Hi Guys,

I have a question with how my orders are being scheduled.

Today's date is 3/27/2009.

Plant settings allow Orders Can Start in the Past

I create an planned order with Basic Finish Date 3/26/2009 and it proposes a Basic Start Date of 3/26/2009

I am confused when i run the scheduling for the planned order, and :

The Production Start Date is 3/27/2009 and Finish Date is also 3/27/2009.

Why is this happening?

Here are the Scheduling Parameters:

(Planned Ord)OPU5: Do not Adjust Basic Dates, Dep Req to Order Start

(Prod Ord) OPU3: Do not Adjust Basic Dates, Dep Req to Order Start