Hi Guy...

My PO release strategies in the header of PO. if user entering multiple plant in item level, the release strategies will not work.

In order to solve this problem, i want to block the User from creating a multiple plant in PO .. how to do that ?

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Mar 27, 2009 at 03:34 AM

    hi

    check is there any user exit available apply your logic and activate.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 27, 2009 at 03:48 AM

    Use BADi - ME_PROCESS_PO_CUST & in this BAdi check during PO creation stage for multiple plants. Give your logic to your abaper & the same can be done.

    Hope the above answers your query.

    Regards,

    Vivek

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.