Does anyone know of a way to limit the MRP planned replenishment quantity to a maximum value? We have sole Suppliers who have a capacity constraint and we do not want to order more than a set amount per week. Any short replenishments would roll into the next week and continue to do so until the replenishments are able to catch up, or the end of the horizon encroaches. We do not want to reduce the Master Schedule to plan less.
Edited by: Michael Kremer on Mar 26, 2009 5:59 PM