Skip to Content
0
Former Member
Mar 26, 2009 at 04:30 PM

Settlement Rule

25 Views

Hi friends.

I have one maintenance order, with two operations. One is performed by the Work Center ELECTRIC, and another by the Work Center MECANIC, and both of them for the same equipment.

Now in the master data of the equipment I have one cost center defined.

I want to sttle the cost of the maintenance order, to the Work Centers and not to Equipment.For exemple, the operation 1 settle to Work Center ELECTRIC, and operation 2 to MECANIC.

Can this be done?