Dear All,
I am using Sales Order base planning.
In my sales order delivery date is come 15.03.2009.
When i run Monthly MRP on Date 18.03.2009.
All material expect Raw material all material are available.
Delivery date is in past 15.03.2009 so,By forward scheduling my system give Planned start date as on date 18.03.2008.
Planned Order Contain Exception Msg :
30= Plan process according to schedule (18.03.09/01.03.09)
07= Finish date in the past
My client also required that with the exception message they don't required planned order.
>If Raw material not available in this situation my planned order also not generate by system.Is it possible?
From my side i conclude following thing:
That Sales order Delivery date in past so system forcefully give planned start date as :18.03.2099 but with the exception msg 30 & 07.In this condition they must have to change Delivery date of the sales order.
But as per my client required if my material not available then my planned order is not create. Is it possible? I am not clear for it.
Edited by: Maulik on Mar 26, 2009 10:43 AM