H/W Migration, Oracel upgrade and Re-org

Hi All,

We are planning to upgrade our old IBM h/w to new IBM Box on which SAP running, Oracle 9i to 10g upgrade and database reorg.

Is it wise to do all to gether at the long weekend or after migrate to new H/W we have to run the system for some days to check that how the SAP performance on new box then upgrade to oracle 10g then monitor for few days then go for reorg. Could you please give your valuable views.

Thanks,

Harish

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 25, 2009 at 04:09 PM

    Hello Harish,

    > Is it wise to do all to gether at the long weekend or after migrate to new H/W we have to run the system for some days to check that how the SAP performance on new box then upgrade to oracle 10g then monitor for few days then go for reorg

    The best way to do so is a system copy and test your performance on the new hardware after all the upgrades .. otherwise you can not do a forecast. The migration from Oracle 9i to Oracle 10g can have many traps, so you have to test it carefully.

    I also wrote a little blog about that topic how you can reduce the manual effort:

    /people/stefan.koehler/blog/2009/02/09/oracle-real-application-testing-with-sap

    So i can only suggest:

    1) Install your new IBM hardware and AIX

    2) Make a system copy

    3) Upgrade the oracle database and reorg

    4) Test your critical processes

    That's the safest way.

    Regards

    Stefan

    Add comment
    10|10000 characters needed characters exceeded

    • Hello Harish,

      > We will do as per your suggesion ..

      No you misunderstood. My suggestion is to make a system copy of your production system to your new IBM hardware and test your critical processes after the upgrade and reorg.

      After all your tests are o.k., you can do the productive migration to the new hardware and upgrade / reorg your oracle database.

      Regards

      Stefan