MRP Run

24 Views

Hi,

I have a BOM with the following structure

Level 1 -> FG Planning Strategy 52

Level 2 -> SFG Phantom Material, No Planning Strategy (lead time : -1)

Level 3 -> SFG Non-Phantom Material, No Planning Strategy (lead time -1)

Let's say I have a couple of sales order with my FG with the following scheduled delivery dates :

14.02.2009 8Qty

15.02.2009 8Qty

27.03.2009 8Qty

I run MRP (27.03.2009)

I am getting :-

(a) Planned Order for 27.03.2009 for 8Qty on FG Level

(b) All Dependent Requirements for SFG Non-Phantom Material (14.02.2009, 15.02.2009 and 25.03.2009 ) are grouped together and one planned order on 25.03.2009 for SFG Non-Phantom is created.

May I know what's the logic behind this?

How do I set the system so that requirements from previous (unclosed sales order - 14.02.2009, 15.02.2009) orders do not appear in today's dependent requirements?

Thanks

Edited by: Jiin on Mar 25, 2009 4:07 PM