Hi,
I have a BOM with the following structure
Level 1 -> FG Planning Strategy 52
Level 2 -> SFG Phantom Material, No Planning Strategy (lead time : -1)
Level 3 -> SFG Non-Phantom Material, No Planning Strategy (lead time -1)
Let's say I have a couple of sales order with my FG with the following scheduled delivery dates :
14.02.2009 8Qty
15.02.2009 8Qty
27.03.2009 8Qty
I run MRP (27.03.2009)
I am getting :-
(a) Planned Order for 27.03.2009 for 8Qty on FG Level
(b) All Dependent Requirements for SFG Non-Phantom Material (14.02.2009, 15.02.2009 and 25.03.2009 ) are grouped together and one planned order on 25.03.2009 for SFG Non-Phantom is created.
May I know what's the logic behind this?
How do I set the system so that requirements from previous (unclosed sales order - 14.02.2009, 15.02.2009) orders do not appear in today's dependent requirements?
Thanks