Hello.
I've just created a process chain that I've scheduled to execute in the future (2050-01-01) as I want to trigger this process chain manually along the year as the execution time is never known.
Now, to execute this process chain, I simply goes into RSPC, double click on my chain, right click on my start and select "Display Scheduled Job(s)". From there, I just repeat my job with an "Immediate" scheduling.
This is what I've done this morning, it worked fine as expected. Now, I'd like to proceed again with the execution of this chain so I goes within the exact same process but then the job crash as soon as it start with the following message:
2009.03.25 10:20:04 Job started 2009.03.25 10:20:04 Step 001 started (program RSPROCESS, variant &0000000036422, user ID BWREMOTE) 2009.03.25 10:20:05 Process PSADELETE, variant MX_008 is not scheduled waiting for event RSPROCESS D5CMCODS3V2RVD13XPIYRW1QE 2009.03.25 10:20:05 Job cancelled
Nothing have changed in my process so I'm quite confused about this...
Any idea?
Thank you & best regards
John.