Can i create two line items in PO with reference to Single PR in third party process

former_member584050
Participant
0 Kudos

Dear experts,

I have one PR which is having 10 quantity , with this PR i want to create Two line items

in PO each line item will have 5 quantity.

User in production entered two line items wrt to single PR, but when i am replicating it system not allowing me to do this.

Please suggest am i missing to choose any option.

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

"but when i am replicating it system not allowing me to do this."

This does not give much details, SAP usually communicates with a user by sending messages, what error message do you get?

former_member584050
Participant
0 Kudos

Hi Jurgen,

Thanks for your time please find below details

in order we have single PR and its line item 10, user has given same PR twice in po for the first line item he he maintained 10 in the same po for 3rd line item same material he has given same PR and he maintained 30 as PR line item number.

When i am replicating same getting below error message

Purchase requisition 10016033, item 00030, does not exist

Message no. 06275

instead of 30 if i maintained 10 i am getting different error like below

Purchase requisition 10016033, item 00030, does not exist

JL23
Active Contributor

thats not a different error, thats the same error, you probably wanted to show something else.

also there is no evidence that you want convert 1 PR item into 2 PO items, each of your PO items is pointing to an individual PR item.

former_member584050
Participant
0 Kudos

Hi Jurgen,

My apologies to you

I misunderstood the issue i am closing the issue. sorry for inconvenience .