Dear All,
My Sales order delivery date is 15..03.2009 and when i run MRP on date 18.03.2009.
System generate planned order with exception msg 30 .
For this palnned order Raw material is also not availabele.
So,it requied solution is that from my side is that Change delivery date of the SO
But my Client requied following thing :
>Ideally, we want SAP to prompt the date of delivery considering forward planning from the date of mrp run, ie. it should take into consideration the material availability and work-in-progress requirements and tell the expected date of delivery, instead of manually someone re-schedules the delivery date.
It is possible in SAP?