Hey gurus,

In preventive maintenance order the basic and scheduled start dates are picked from the maintenance plan. Now the actual start and end dates are in display mode. My client wants an overall completion time and date of the preventive order and not of individual operations. Also at the end of the month they want to see the total time spent on preventive maintenance. Can you suggest any way to sort out the above problem.