Hi All:

I have a couple of questions.

1. We created some new plants in R3 and CIFed it over to APO. After executing the product hieuristic in Product overview and PR was created, I did not find the PRs transferred to APO. I found the reason to be that I had to enter the record in 'Maintain View for Distribution Definitions' in APO IMG, I did not find the PR to be transferred. How can I transfer the PR that is already there in APO and not in R3?. I tried to re run the creation of IM for PR and activate it in R3. That did not help.

Pl. help.

Thanks

Narayanan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Mar 25, 2009 at 06:47 AM

    Hi Narayanan,

    1) In IMG setting, use the following menu path SAP SCM Impl guide > APO > Supply chain planning > SNP > Basic settings > Configure transfer to OLTP systems

    In this, under deployment, select the purchase requisition and say either "Immediate transfer" or "Periodic transfer". In Immediate transfer, the PR generated will get transferred to R/3 system immediately. In Periodic transfer, you need to manually control the transfer via change pointers using t-code /n/sapapo/c5.

    2) Regarding your second query, you can make read of the books

    a) Production Planning with SAP APO-PP/DS by author Jochen Balla, Frank Layer

    b) Supply Chain Management with APO by Jorg Thomas Dickersbach

    c) The SAP APO Knowledge Book by Wolfgang Eddigehausen

    Regards

    R. Senthil Mareeswaran.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Narayanan ,

      In addition to setting that Senthil has mentioned (immediate / periodic transfer) you need to maintain the distribution defenition for purchase requisitions. The menu path you have mentioned is right. The distribution defenition can also be accessed using transaction /n/sapapo/cp1. You will not find the purchase requisitions there. You just have to maintain a distribution defenition for "External procurement" . The location willl be the location in which PR's are generated and the logical system will be your R/3 system . In addition to there must be an active integration model for purchase requistions (PR's and PO's) for the material-plant in question.

      Thanks

      Saradha

  • avatar image
    Former Member
    Mar 25, 2009 at 02:40 AM

    Sorry:

    The other question is,

    Is there any good SCM book that I could buy ?

    Thanks

    Narayanan

    Add comment