Hi:
I am wondering if anybody could help me?
In my repetitive environment, I have two production versions where i would like to split EACH individual requirement to what the percentages dictate in the quota arraignment. My situation right now, SAP is taking ALL requirements and split to what the percentage dicates in the quota arraignment, but i'd like to split by individual requirement.
Is it possible to perform the split by each individual requirement?
The example below is what is needed.
For example:
Quota Arraignment
Prod version 0001: 75%
Prod version 0002: 25%
Requirement #1: 12 pieces
Planned order 1 = 9 pieces
Planned order 2 = 3 pieces
Thanks Patrick