SSM 7.0 - integrating PPO (Project Portfolio Office) tool with SSM 7

Former Member
0 Kudos

Hi All,

Has anyone loaded data from PPO (Project Portfolio Office) tool into SSM 7.

This is for loading initiatives and milestones in SSM 7.

Is there any standard way of doing this?

Thanks in advance.

Kind Regards,

T

Accepted Solutions (0)

Answers (1)

Answers (1)

Bob_McGlynn
Product and Topic Expert
Product and Topic Expert
0 Kudos

Taarig,

There is no current method in SSM for transporting project data into the Initiatives tab.

Data for Initiatives are stored in the relational database associated with SSM and so it could be possible to build a customization to do something like this.

A big challenge, if you were interested in customization, would be developing a mechanism to import and update information about initiatives. At the very least, there would need to be a standardization on how teams put together their individual MS Project plans so data could be exported.

There are requests for this functionality for future releases of SSM.

Regards,

Bob