Hello Experts,

Can anyone let me know what is goin wrong in my CJI3 report or am I missing any setting for dynamic selection???

I need to have CJI3 report with selection on workcentre level, but when I run the report I shows me the cost of all the Workcentre. I need to have cost of single workcentre.

Regards,

Tushar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 24, 2009 at 08:38 AM

    in the CJI3 screen enter network number and not the project definition

    set dy sels for net act master data for work centre

    execute

    you should be ok

    unfortunately in CJI3 you do not get work centre as a field

    you can double check results using CN47N