MRP Lead Time Scheduling

49 Views

Dear experts,

I have a material with the following BOMs

BOM A (FG)

Component B (Phantom Item - SFG) , Lead time : -1

BOM B (Phantom Item - SFG)

Component C (ROH), Lead time : 0

When I run my MRP, the planned order for the components were generated as below :-

Material A 23.03.2009

Material C 23.03.2009

This is wrong, considering that Component C should take into account the lead time on its parent (Component B) and should propose a planned order on 22.03.2009.

I'm not sure what causes this, has anyone experience on this before?

Thanks in advance.