Dear experts,
I have a material with the following BOMs
BOM A (FG)
Component B (Phantom Item - SFG) , Lead time : -1
BOM B (Phantom Item - SFG)
Component C (ROH), Lead time : 0
When I run my MRP, the planned order for the components were generated as below :-
Material A 23.03.2009
Material C 23.03.2009
This is wrong, considering that Component C should take into account the lead time on its parent (Component B) and should propose a planned order on 22.03.2009.
I'm not sure what causes this, has anyone experience on this before?
Thanks in advance.