Error whic saving the project (related to cost center & work center)

Makal
Active Contributor
0 Kudos

Dear Friends

I have released the WBS, confirmed the activity (it has two activity element with XYZ work center).

I have confirmed the activity. When I try to save the project (system does cost calculation), I'm getting following error:

"Work center XYZ in Plant 1000 has no cost center"

Data in Work center is perfect. Cost center is present, activity type is correct.

But still getting this error.

Any idea why? What could be the problem.

Accepted Solutions (0)

Answers (2)

Answers (2)

Makal
Active Contributor
0 Kudos

solved

virendra_pal
Active Contributor
0 Kudos

can you please write error number

Makal
Active Contributor
0 Kudos

Thanks for replying Virendra.

Actually its not error, it's warning.

For an activity element, I checked plan costs (CTRLF10 & CTRLF11).

When I do CTRL+F10, system throws warning (pop-up) saying "Messages were issued when costs were calculated(See log)".

When I check log (Extras>Logs>Cost calculation), I see three warnings specifying same thing. They say "Work center XYZ in plant 100 has no cost center".

I checked my cost center, it has cost center.

Any solution for this?

Makal
Active Contributor
0 Kudos

same kind of activity, with same work center & activity type is calculating the costs correctly without any warning.

I mean same kind of activity element with same work center & activity is working well within another WBS & it's not working in other WBS. This is really confusing me.