hai ,

i have worked in 001 client and configured self service procurement completely.and later i was doing plan driven procurement and maintained v_t160pr ,and v_t160 ex and run the report bbp_extrun_transfer in r/3.but the system had given a warning message as below

sap event management communication aborted,no AOTS defined.

*Eh creation not permitted:AOT evaluation skipped

*event message sending not permitted:event type evaluation skipped.

i thought that i have missed some configuration in r/3.am i correct?if it is, can anyone please give me the suggestions what are all the remaining things i have to configure in r/3.