Error in Milestone confirmation in PP-PI

132 Views

Dear Friends,

Que 1) In my recipe i have given milstone confirmation with automatic GR to last operation.And all the preceeding operations as Confirmation required but not necessary. When i am confirming that operation with COR6N, confirmation with auto GR done. Acoording to concept of milestone confirmation, the operation before that should confirmed and give the staus as CNF in process order. But here they are not confirmed. How to do this?

Que 2) If i want to do individual confirmation for each operation, then how to do this?

Dear friends give me your useful solution for above.

Regards,