Hi Experts,
Our customer wants that if line item is added to PR and PO on ECC side, it should be added to SC as well. I am sure you can't change apporved SC for which follow on document is created. But if someone did similar kind of requirement.
Here is requirement.
> SC has 2 line items.
> PR is created in ECC for 2 line items after SC is apporved.
> User added 3rd line item in PR on ECC side.
> Customer wants this line item should be added to SC as well.
Please advise.
Regards,
Kamal