in my scenerio i am using forward scheduling with strict bottom up approach for all network.

network A

act 1 FS (1day) act 2 fs (1day) act3.

start date 23.3.2009.

act 1 starts on 23.3.2009

act2 starts on 23.03.2009 but i have given 1 day float?

act 3 starts on 24.03.2009.

All the Duration of the subsequent activities are coming correctly, but the 2nd actvity why the float is not taken of one day I cannot understand.

If i give act1 FS(2 days) to act2.

then the act 2 starts at 24.03.2009. I do not know why this is eating up one day for the second activity.

Please can anyone help me.