Hello everybody:

I would like to maintain the activity price with a foreign currency using KP26. Say, my controlling area currency & company code currency are both USD, but I want a price in EUR. During KP26, there is no place for me to select the currency key.

Is this requirement achievable in SAP?

Pls advice. Thanks.

Andy

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Andy,

Yes, you can definitely plan in any currency other than Controlling Area / Company Code currency. You need to configure your Planning Layout accordingly. Pls follow the link below and check "Currencies in Planning" under Cost Center Planning Scope for further clarity...

http://help.sap.com/saphelp_47x200/helpdata/en/5b/d2200743c611d182b30000e829fbfe/frameset.htm

Pls revert back for further explanation...

Srikanth Munnaluri

Former Member
0 Kudos

Hi

Guess - try in KP26 under Settings - User Settings - Report currency

Else try creating a new planning layout in KP65, assign to planner profile and set planner profile in KP04

Thank You,

former_member200271
Participant
0 Kudos

Hi:

I have tried according to your reply, but it does not help.

The tcode used to created layout is KP75 (not KP65), and there are only possibe to select planned activity price by COAr currency or object currency, but in our system, the two currency are the same.

Andy