Hi,
i hv maintain two prod. version.& in each version maintain alternative bom & routing.when i do mrp run or crate prod order manualy system automaticaly select bom 4m first version & give pop-up window to select routing.........i want to select version manualy &bom also.............system not ask me to select prod version......hw to solve ? i m not using rep manufacturing.... thanks
Edited by: santosh N on Mar 21, 2009 6:10 PM