Hi..

Need one clarification.

Whether a CO document is generated for activities confirmed against a Production Order.

I understand that a CO document in respect of activity can be generated only when WIP / Variance are settled.

Please confirm.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Swapvik,

Yes, CO document gets posted at the time of confirmation of Activities.

You can see that by going through the Cost Analysis of the Order and by double clicking the actual confirmation line. System will take yout to the CO Document posted.

You can see the same doucment in KSB5 also.

Pts appreciated.

Srikanth Munnaluri

Edited by: Srikanth Munnaluri on Mar 21, 2009 5:22 PM

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Swapvik,

Thank you very much for your "2" points. I hope my answer could give you complete solution for your question. I would be glad if you can share with me the other options you found for resolving your question which made you mark the thread as "Answered".

Waiting to hear from you....

Regards

Srikanth Munnaluri

Edited by: Srikanth Munnaluri on Mar 22, 2009 11:35 PM

Former Member
0 Kudos

Yes Thanks for the response.

Actually, I went to the settlement document and checked on the Relationship browser in Environment -> Original Documents..

I could see the confirmation document, which had CO document relationship also.