Mar 21, 2009 at 05:16 AM

capacity distribution

21 Views

We have one requirement of 100 hours and production lead time sheduled in MRP is 6 days ,Now we know that on each day 18 hours are available as operating time then still system is distributing capacity as 16.77 hour for each day.My question is why system is not taking full operating time for capacity distribution? It should show distribution like 18 hr for 1 day ,18 hr for 2 ,18 for 3 ,18 hr for 4, 18 hr for 5 day and rest 10 hr for last 6 day.