on 03-20-2009 7:19 AM
Dear all,
I have created a validation rule to validate the company code used between the Project Definition and WBS Element, and it must be the same. This validation is working
I assigned it in OPSA for the Project Profile that I am working on. The validation was carried out successfully too.
However, in the configuration in OPSA, there is only one field for assignment of validation rule created for one project profile.
Now I have more than one validation required for the same Project Profile. I need to carry out few validations. Is there any other way (in configuration) that I can do to achieve this?
Pls help.
Thanks.
Best rgds.
You create all your validations as validation steps (step 001, step 002...etc) under single validation name...and assign that validation name to the profile....but remember the validation will be executed sequentially from step001 to step00n...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.