on 03-20-2009 4:22 AM
How to Upload the Open Production orders in production system during cutover activities.
my client is having 1000 open production order(WIP), during cutover activies how to upload this in production.
Please guide me
Regards
Sunil Patil.
Dear all,
I did not get how we can upload the wip.
1. If the open production orders means process is going on. Activities/Order are going on not confirmed means how we can upload
2. If activities/Order are confirmed then how can we upload the wip
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I somewhat agree with what Raj has to say. Something which is already in process how can that be uploaded, how can one compensate for the time which has been consumed in the production activity.
I hope Rupesh Brahamakar sir would throw light on this issue, as most of us are under the dillema at the time of Cut-Over activity.
Sir, hoping your valueable inputs.
Regards,
Harris
hi,
1)Identify open production order number,
2)calculate material(ROH,HALF..) issued , activity for open production order,
3)upload stock for all rawmaterial, semifinished consumed for that open production order,
4) issue(consume) against open production order ,
5) calculate WIP ,
6) post WIP in privious period,
i hope this will help...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.