Former Member
Mar 20, 2009 at 04:19 AM

Types of Scheduling

287 Views

Daer SAP PS Experts !

Please help me out in the following sitiuation.

We have forward scheduling in out company : Such That the users knows the start date of the project and they put in the relationships in the activity and contraints.

They want to arraive at the dates of the project ending via scheduling .

What is the project profile should be used from the following :

Sched. scenario What should I choose : 1. bottom up 2.Top down 3. Free Scheduling

They Will put the dates in the Sub level networks and relationships which will add up to the dates of the Projcet Level. So should this be bottom Up?

Regards,

CS