Quantity Change At process order?

Former Member
0 Kudos

Dear Guruji

I am Realse Process order as per Std BOM. But at conformation Tranziction I am Changed Planed Quantity.How Can I tressiblae That only that Process order Which is change in planed quantity at Goods Issue?

Accepted Solutions (1)

Accepted Solutions (1)

former_member196398
Active Contributor
0 Kudos

Dear,

There is no tracking mechanism in SAP. If you dont want users to change the component during confirmation, then you create a transaction variant for CO11N transaction, and define in such a way that Component quantity field is greyed out and also delete button is also removed.

If you search this Forum you will find suitable threads explaining the process of creating transaction variants.

Regards,

Prasobh