on 03-19-2009 12:29 PM
Hi,
Is it possible to spilit planned order(PE order type) on weekly basis? if yes kindly give the details of configuration settings.
Dear Praosh,
my requirement is like this i entered the PIR on monthly bucket is there any setting available by using which i can spilit the requirement on weekly basis, i have this option to enter the PIR on weekly bais, or spilit the PIR on weekly basis....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Prasobh and Mangalraj,
Thanx alot for sharing ur knowledge and experience with me.....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Syed,
In MD62 transaction You can split your PIR into weekly basis, In the Schedule Lines tab and save the PIR. Once this is done, run the MRP in Delete and Recreate data mode, new planned orders would get generated automatically based on the PIR.
Hope you have not firmed the PE - Planned orders(No Manual Changes in Planned order or You are also not using Planning time fence).
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.