Skip to Content
0
Mar 19, 2009 at 11:31 AM

Costing variant 2222 is not permitted

47 Views

Hi Experts,

Can anybody solve this error

I was trying to assign costing variant to production order type in OPL8 but facing following error.

Costing variant 2222 is not permitted

Diagnosis

Each costing variant refers to a costing type via settings in customizing

The following parameters are defined in each costing type:

An indicator which specifies whether it is used to calculate planned or actual costs.

A key which determines the object to which the costing refers (for ex. material, production order,)The costing variant that you have entered is invalid for one of the following reasons:

The costing variant that you have specified for calculating actual costs in the order is defined (via the corresponding costing type) for calculating planned costs.

The costing variant that you have specified for calculating planned costs in the order is defined (via the corresponding costing type) for calculating actual costs.

The reference object of the corresponding costing type is not a production order.

Procedure

1. Check the assignment of the costing variant to the costing type. Change the assignment if necessary.

2. Change the costing type data, if necessary, by pressing the function key Detail (next to the costing type) and making the necessary changes.