Hi Gurus,
We have April 9th as holiday at one of our plant but system is pacing orders with first date, avalability date on the 9th of April. This should not be possible for that particular plant since it is closed for easter that day.
I have checked Factory calendar which is assigned to that plant, and there 9th april is showing as off day but in Holiday & Public holiday calendar it is not!! Is this can be reason or else kindly comment.
Thanks in advance!
Regards
Bawa