Mar 19, 2009 at 10:55 AM

Exclude a Production Order Type during MRP Run

935 Views

Hi Gurus,

We have a scenario wherein I created a Production Order Type (ZCR1) which is used for Crushing of Scrap Material. I have certain material code for the output Crushed material which has its MRP type as ND. The components are Semifinished Goods which have MRP Type PD. We have not define separate material code for the Semifinished goods that are rejects but instead define an Scrap Storage Location.

However, when MRP run is executed, the quantity in the Production Order of ZCR1 is reflected as Reservation in this Semifinished product which gives wrong quantity in production. Please let me know if there are ways to exclude this production order in creating such reservations and exclude in MRP Run.

Thank you,

Raymond