Weekly lot size procedure

1035 Views

I've a scenario where my client requires raw material to be procured only weekly. That is monday of every week material for that week alone must be procured.

Eg. Header material = A

Raw material = b

Now requirment for header material in week 1 (i.e 23.03.09 to 27.03.09) = 100

and requirment for header material for week 2 (i.e 30.03.09 to 05.04.09) = 100

Now what setting has to be done in raw material "b" so that PR for that material has delievery date of 23.03.09 for 100 nos and 30.03.09 for 100 nos.

I have tried lot size weekly but in that case it is combining the the qty as 200 for 2 weeks and thenm procuring the material.

PLease help urgently