Hi,
I am using planning strategy 40 for MTS.
Scenerio : FERT1 in PLANT1 PRI created as 10000 each for week1 to week5. Total of 50000
After MRP run non-convertable planned order create for each week requirement.
Sales order created for 15000 and after MRP run planned order created with conversion indicator of 15000 qty. There is no reduction in PIR or planned order created from pegged requirement of PIR.
Requirement : PIR should be reduced 35000 and respective planned order should be removed created from PIR in earlier MRP run.
Please suggest solution.