commitment and budget value updation in R/3 from Shopping cart

17 Views

Hi,

I implemented extended classic scenario of SRM, so I create shopping in my SRM system and not anymore purchase requisition in SAP R/3. As a consequence in SAP R/3 all the controlling standard reports don't display any data about commitment from shopping basket.

SAP SRM only does budget check for shopping carts, but it doesn't post to funds management after the shopping cart's creation and approval. Our client requirement is to update commitment in funds management just after the approval of the shopping cart, just like purchase requisitions of MM does. Does anybody have passed through this problem? How can I solve it?

How can I get commitment from SRM in a standard or custom way?

Thanks in advance,

Santosh V. Fhalke