Skip to Content
0
Former Member
Mar 19, 2009 at 06:44 AM

Rescheduling at material level or MRP controller level

63 Views

Hi,

I have come across one scenario:MRP need date and PO delivery date are within one week no exception message will be generated.

We can acheive this by maintaining tolerance values in OPPQ/OMDW. But problem is user wants this functionlity for purchased parts only and not for Inhouse mfg. parts.

As per my knowledge if we maintain tolerance values in OPPQ and select all recipts elements these values are applicable for those one also.

To overcome this issue is there any standard config exist in SAP? or else please let me know any enhancement to resolve this issue

Thanks in advance for your valuable input

Regards,

Alex