Fill actual dates in network activity with BAPI

former_member598788
Discoverer
0 Kudos

Hello,

I'm creating new network activities with BAPI_BUS2002_ACT_CREATE_MULTI.

I must fill actual start date and actual end date, in cj20n fields: AFVGD-ISDD and AFVGD-IEDD. How can I populate this fields with BAPI? Perhaps should I use another FM?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member598788
Discoverer

Solved, I used BAPI_NETWORK_CONF_ADD and fields EXEC_START_DATE and EXEC_FIN_DATE.