Skip to Content
0
Former Member
Mar 19, 2009 at 04:47 AM

Subcontracting

161 Views

Guys

This is a scenario

Subcontracting pur req is created by System through MRP run for Material A

Material B is supplied as a component to the vendor

Pur req is converted to purchase order for material A

Then in MD04 for Material B - it is shown as SubReq

For Material B

Rounding Value and minimum lot size are maintained

Base unit of measure(KG) and ordering unit of measure(KM) are different

Problem is like this

When i create sub contracting purchase order for large quantities(Material A) say 2000 Kgs

Then Material B gets two requirements(SubReq) in place of 1

Say 500kg each where as desired one is single requirement as 500Kg

If i create for small quantities say 10 kg

Then I get only one requirement (SubReq) for Material B

Is it the effect of rounding value ?

What is the effect of maintaining both Rounding value and Minimum lot size ?

Please give your inputs

Thanks

SVP