While doing Business completion of Maintenance order I was getting following error -
Unprocessed future change recs for order 10001146 prevent del. flag/completion
And, after analysis I came to know that there was following error in one of the time confirmatio ::
Budget for WBS element 5011.A.50459.001 was exceeded by 12,112.03 INR in document item 001 Order 10001146 .
Can any one guide how to correct the same?
Thanks in Advance
Regards
DM
Edited by: Deepak M on Mar 19, 2009 12:10 AM
hi
i think your confirmation has not been saved.increase the budget amount for the WBS element ,then confirm the operation ,then try to do the business completion .
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.