I have maintained the DMR at lot creation and also maintained at inspection header level
as lot level and attached the corresponding DMR to it.
My DMR rule:
Stage 10
OK
No of Inspections : 1
New ins stage : 20
NOTOK
No of rejections : 1
New ins stage : 10
Stage 20
OK
No of skips 1
New ins stage 10
NOTOK
No of rejections 1
New ins stage 10
It is perfectly working fine for lot creation level as I can see some skip lots generated in ins.lots and it directly move to unrestricted use .
My problem is when I did for DMR at UD level and also maintained in ins plan header as lot level attached with right DMR to it.I have applied the same above rule and try to see the difference from lot level to UD level but I couldnu2019t figure out.
I have got all my inspection lots continously skipping.and material is directly moving to unrestricted use as same as lot creation level......is tht anything do with rule?
Please explain step by step process like how UD level works in DMR and let me know the difference of lot level and UD level
Please advise.