Dear Gurus,
Given below is a scenario
An activity has a duration of 10 days and work of 100 m3. start date: 1st Apr & finish date is 10th Apr. And activity is linearly distributed.On 5th Apr, if confirmation is 40 m3 of work completion instead of a planned completion of 50 m3, then on re-scheduling, system should propose a new forecast finish date for the activity, keeping the planned dates same.
pls suggest the configuration/customization required.