Delayed Distribution Demand in SNP interactive planning

21 Views

Dear Guru,

I am facing a problem in APO SNP concerning delayed Distribution Demand in the interactive planning and I would highly appreciate some help.

We are loading orders from R3 to APO SNP via XI. We use Idocs (type POAPS_SAVEMULTIPLE2).

The BAPI called by APO to load the Idocs is BAPI_IDOC_INPUT1 (which calls IDOC_INPUT_POAPS_SAVEMULTI2 and also BAPI_POSRVAPS_SAVEMULTI3).

The sending and the receiving locations are SNP markets.

The problem is that everytime, the availability/requirements date of the distribution demand is delayed of one week in the Sending location view.

In the receiving location view, the availability/requirements date of the distribution receipt is correct (Requested date + transportation Lead Time).

Have you got any idea of the reason of this ?

Thank you very much for your answer.

Rgds

Fabien