LTP : how consider material with mrp type ND

Former Member
0 Kudos

Dear guru ,

I have a material donu2019t consider for mrp using mrp type ND.

But also LTP donu2019t consider this material.

How can I consider this material for Long Term Planning ?

Does exist any workaround ?

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

As far as the MRP type is ND, you will not be able to include such material in the LTP.

Change the MRP type to PD for example. Then, with custom created Material Status you can include materials in LTP and exclude it from MRP.

BR