In my current scenario i'm able to see load of process orders against the workcenter in CM01. My requirement is to do capacity levelling at the planned order level.
I have created Production version also & attached to the planned order. Still in CM01 no load or planned order is shown on workcenter.
when i convert it into process order then it shows load / process order.
pl.let me know how i can do the capacity planning at planned order level.
Thanx & regards,
dev
Thanx a lot to all !
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dev,
Check the settings in Control key for Operations, you have to check the box for Capacity requirements and also you have to define your work center " Relevant for Capacity rquirements".
It will solve you issue.
Thanks
Satya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try capacity planning at planned order level in MF50.
As per my knowledge, you will not able to do the same in CM01.
Regards,
Tejas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.