Hi CO Experts,
I am trying to settle to a G/L with Cost Center Assignment. The only way that allows me to proceed now is by manually maintaining the G/L - Cost Center Assignment in tcode OKB9.
If I don't maintain a Cost Center in OKB9, when I settle my Maintenance Order, an error showing "CO Object assignment required".
The question is, How do I maintain a cost center assignment for the G/L in the settlement rule without manually assigning it in OKB9. I want to assign the Cost Center maintained in the equipment master data inside the maintenance order.